OWNER:
Florida Department of Transportation
1221 Rinehart Road
Sanford, FL 32771
PROJECT
ENGINEER:
Dyer, Riddle, Mills & Precourt, Inc.
1505 East Colonial Drive
Orlando, FL 32803
GENERAL
CONTRACTOR:
Martin K. Eby Construction Company
2752 Country Club Road
Sanford, FL 32771
DESIGN/CONSTRUCT
CONTRACTOR:
Synergy Earth Systems, Inc.
The Central
Florida Greeneway, also known as SR 417, is a multi-lane toll road
serving the perimeter of Orlando, Florida. Construction of SR 417
has been completed in stages that initially began in the 1990’s.
A contract to construct Section No. 2 of the highway, which is located
northwest of Orlando near Sanford, Florida, was awarded in 2000
and construction was completed in 2002. The final alignment of SR
417 is such that a significant depth of compressible soils underlies
a portion of its 2.6-mile length. Some boring logs indicated that,
at the interchange of SR 417 with County Road 46A, silty, organic
peat soils extended to a depth of nearly 100 feet. When encountered
in their original depositional state, these soils are typically
considered problematic due to their weak, compressible nature. To
address the stability and settlement issues pertaining to these
foundation soils, the project contract required that, for approximately
2,500 linear feet of the proposed alignment, the contractor partially
excavate the compressible soils to a depth of 20 feet and then place
select backfill in the excavation. Vertical (wick) and horizontal
drains and geogrid reinforcing were utilized in conjunction with
a surcharge in the design shown in the plans.
The general
contractor asked SES to prepare an alternate design that eliminated
the requirement for partially excavating the compressible soils.
This approach, which had successfully been used in the past by SES,
addresses the stability and settlement related issues pertaining
to construction over peat by modifying these soils in place. The
project engineer had previously indicated that it would approve
such an alternate design only if several design criteria could be
met. Chief among these criteria was that the alternate design must
address the primary and secondary settlement of the compressible
soils such that under the proposed finish grade, 100% of the primary
consolidation of the compressible soils be achieved, and that the
secondary settlement be advanced to the point that not more than
4 inches of post-construction settlement would occur in 10 years.
The other primary design criteria established by the project engineer
was that the alternate design be completed utilizing a slope stability
factor of safety for the long-term condition of 1.5.
After preliminary
calculations by SES indicated that the alternate approach was technically
and economically viable, the general contractor entered into contract
with SES to finalize the design and, pending approval of the design
by the owner, to perform certain construction activities. After
an exhaustive series of design calculations had been completed,
the project engineer approved the alternate design and construction
began on the affected portion of the project in June 2000. SES was
responsible for installing all wick drains as well as for providing
construction management services to the general contractor to oversee
installation of all geogrids and instrumentation. The approved alternate
design consisted of a biaxial geogrid and multiple layers of uniaxial
geogrids, and over 415,000 linear feet wick drains installed on
a triangular spacing of six feet. The alternate design also utilized
a 5-foot high, 120-day duration surcharge to achieve the required
overconsolidation of the underlying compressible soils. The instrumentation
plan presented in the contract drawings, including piezometers,
settlement plates and slope inclinometers, was not changed by SES
and was used to monitor the response of the foundation soils to
the construction loading. The embankment and surcharge were successfully
constructed by October 2000. In May 2001, after analyses of the
instrumentation showed that the foundation soils had achieved the
required level of consolidation, the general contractor was given
clearance to remove the surcharge. County Road 46A was then paved
and opened to traffic while the balance of the work was being completed
on the project.