OWNER:
Mississippi Department of Transportation
401 North West Street
Jackson, MS 39201
PROJECT
ENGINEER:
Tanner Construction Company
677 Pecan Grove Road
Ellisville, MS 39437
SEGMENTAL
WALL DESIGN/BUILD COMPANY:
Synergy Earth Systems, LLC.
26240 Equity Drive
Daphne, AL 36526
There is
a stretch of I-59 in Laurel, MS that has a series of sharp curves.
Over the years, this winding section of highway has seen its share
of accidents. To alleviate the sharp curves, this section of I-59
was redesigned. The new highway design called for a segmental
block wall to be used beneath one of the bridge abutments and
along the side of the highway. The Mississippi DOT (MDOT) saw
the aesthetic and economic benefits of using a segmental block
wall system over other wall types. MDOT also selected a section
of highway near the segmental block wall that would utilize a
wire faced temporary wall system.
Synergy was
selected by Tanner Construction to provide design/build services
related to the segmental block and temporary wire faced walls
on this project. During the design of the segmental block wall,
Synergy was able to work with Tanner Construction to incorporate
a backfill material that was much more cost effective that the
standard #57 Stone used on most DOT projects. This allowed for
some cost savings and reduced the chance of delays due to a lack
of #57 Stone being available in the area. Another design item
that Synergy helped out with related to the soil behind the backwall
of the bridge abutment by the block wall. MDOT had a concern about
the possibility of the soil behind the abutment backwall pushing
enough to cause the drilled shafts beneath the abutment to move.
Synergy proposed the use of a welded wire form pressure relief
wall behind the abutment backwall to keep the soil pressures off
of it. This proposal was accepted by MDOT and incorporated into
the design drawings produced by Synergy. The final wall drawings
called for about 10,000 sf of segmental block wall and about 1,500
sf of wire faced walls. The first phase of construction was completed
in the fall of ’07 and the second phase is expected to start
and finish in the Fall of ’08